Skip to content
Sysfacts
All case studiesSTORAGE MIGRATION · ENGINE DEVELOPMENT

Steyr Motors

30 TB switched in two hours. No test run lost.

THE CUSTOMER

Steyr Motors develops engines for industrial and marine applications. Individual test cycles run for days or weeks.

2023
SCOPE AND OUTCOME

The project at a glance.

PROJECT PERIOD · 2023
hours for the cutover itself
2
virtual machines, 30 TB
100
01

The challenge.

The existing storage was approaching end of support. Around 100 virtual machines and 30 terabytes of data needed to move to a new storage platform. With test cycles lasting days or weeks, no measurement series could be lost. The internal team needed to remain focused on its specialist applications.

THE REQUIREMENT

No test run must be lost.

02

Our contribution.

We handled system architecture, implementation and hypercare. After reviewing requirements, we prepared the new storage layer and migration, transferred most of the data in advance and supported the environment after the cutover.

  • 01

    Clarified test-bench software dependencies and identified critical workloads and their latency and throughput requirements

  • 02

    Kept the virtualisation layer and changed only storage. Most of the 30 TB was transferred in advance while testing continued

  • 03

    Tested and documented every step, with a rollback point

  • 04

    Aligned the window with test cycles and scheduled it for a weekend. Sysfacts carried out the work while the internal team continued its existing projects

03 · THE BENEFIT FOR THE CUSTOMER

No test run was lost. The storage cutover itself took two hours, while the internal team could continue with its ongoing work.

TODAY

Project completed after hypercare

The renewed storage platform supports the existing applications and has capacity for additional test rigs. Sysfacts supported the migration through the hypercare phase. Once this was complete, the environment moved into the customer’s regular operations.

PROJECT AND TECHNOLOGY

Implementation in detail.

01

Original system

The existing virtualisation used HP 3PAR storage approaching end of support. Around 30 TB had to be transferred without losing active measurement series from the test-bench applications.

02

Target environment

The virtualisation layer remained in place. Storage moved to VMware vSAN. This was a storage migration within the VMware environment, not a change of hypervisor.

03

Preparation and data transfer

Latency and throughput requirements for critical workloads were recorded. Most data was transferred in advance while testing continued. The steps were tested and documented with rollback points.

04

Cutover window

The actual cutover took two hours over a weekend aligned with test cycles. Preparation and delivery spanned four weeks. Sysfacts carried out the change while the internal team continued its existing projects.

“With Sysfacts, we were able to renew our infrastructure without a single second of downtime. That is not just technically impressive. It means we could continue our engine development without compromise. It was exactly what we needed.”
Alexander Brunner Head of IT · STEYR MOTORS AG Translated from German
THE FIRST STEP

Facing a similar task?

We discuss your circumstances and identify which experience from this project is relevant to yours.

A short description is enough. You do not need technical documents for the initial enquiry.