Original system
The existing virtualisation used HP 3PAR storage approaching end of support. Around 30 TB had to be transferred without losing active measurement series from the test-bench applications.
30 TB switched in two hours. No test run lost.
Steyr Motors
Steyr Motors develops engines for industrial and marine applications. Individual test cycles run for days or weeks.
The storage beneath the existing virtualisation platform was approaching end of life. A storage failure could have meant losing an entire measurement series. Steyr Motors set the date. Sysfacts handled technical delivery so the internal team could focus on business applications.
No test run must be lost.
The cutover itself took two hours. Preparation and delivery spanned four weeks. The platform can accommodate additional test benches.
The existing virtualisation used HP 3PAR storage approaching end of support. Around 30 TB had to be transferred without losing active measurement series from the test-bench applications.
The virtualisation layer remained in place. Storage moved to VMware vSAN. This was a storage migration within the VMware environment, not a change of hypervisor.
Latency and throughput requirements for critical workloads were recorded. Most data was transferred in advance while testing continued. The steps were tested and documented with rollback points.
The actual cutover took two hours over a weekend aligned with test cycles. Preparation and delivery spanned four weeks. Sysfacts carried out the change while the internal team continued its existing projects.
“With Sysfacts, we were able to renew our infrastructure without a single second of downtime. That is not just technically impressive. It means we could continue our engine development without compromise. It was exactly what we needed.”